Last week at the University Boulevard construction site, Schiralli Construction Corporation completed the final road pour of the project. The eastbound lane remains closed to traffic while it undergoes a curing period. Additional cones and barricades have been placed between the lanes.
This week, the crew will conduct miscellaneous clean up, pour curb and gutter, and finish dirt work for the sidewalk pour, which is scheduled for next week.
###